Study of section & block outfitting to support production planning
Saranki, Toni (2019)
Saranki, Toni
Åbo Akademi
2019
Julkaisu on tekijänoikeussäännösten alainen. Teosta voi lukea ja tulostaa henkilökohtaista käyttöä varten. Käyttö kaupallisiin tarkoituksiin on kielletty.
Julkaisun pysyvä osoite on
https://urn.fi/URN:NBN:fi-fe202001233143
https://urn.fi/URN:NBN:fi-fe202001233143
Tiivistelmä
This thesis focuses on providing more accurate and reliable data for production planning of section- and block outfitting in shipbuilding industry through specific installation time –measurements. Additionally, a current state analysis was conducted and process measurements were tested for future implementation. This work may interest readers, who want to know more about the challenges related to outfitting production and see these facts backed up by numbers. From theory perspective, a heavy emphasis is on (key) performance indicators, waste and variation.
The methods for conducting the study are practical by nature but theory is used to explain results. Data has been collected through interviews with stakeholders and measurements have been performed to support the validity of the first mentioned.
The obtained installation times for section and block outfitting are by far the most valuable contribution since they have enabled predicting workloads much more accurately and thereby assisting production planning. All the future yard outfitting schedules are based on the installation times provided in this thesis. In addition, these have been utilized as the basis for calculating future investments. Otherwise, more insight is provided on reporting to information systems, detail design and variation within production.
Meyer Turku aims to double its production tact within the next five years. This study partly enables evaluating the sufficiency of existing development projects i.e. gap plans. The area phase should be similarly studied though to reach holistic understanding. For the body of existing knowledge on topic, a new measurement technique, utilization of reference times, adds to practical examples for easing work analysis in highly manual circumstances with lots of variation e.g. metal workshops, in turn saving money. Avhandling om block- & storblockutrustning för att stöda produktionsplanering
Syftet med denna avhandling är att stöda produktionsplanering inom block- och storblockutrustning på Meyer Turkus skeppsvarv och kunna bidra till en mera balanserad arbetsbelastning inom produktion. Avhandlingen omfattar inte områdesutrustningen. Avhandlingen kan vara av intresse för dem som vill läsa mera om utmaningar inom utrustningsproduktion och hur man kan kombinera arbetsstudier med teorier om nyckeltal, identifiering av slöseri (Mura, Muri & Muda), variation och flöde i enlighet med Lean-metoden.
Avhandlingen omfattar fyra forskningsuppgifter: undersökning av utgångsläget genom intervjuer och processmätningar, mätningar av installationstider, undersökning av olika indikatorer samt rekommendation för framtida användning av nyckeltal. Avhandlingen bygger på skribentens tidigare undersökningar om block utrustning utförda sommaren 2017 och 2018.
Mätningsmetoderna baserar sig på sådana metoder som använts inom tidigare arbetsstudier, men denna avhandling innehåller ett nytt koncept för att underlätta insamlingen av rådata. Konceptet skapades för att kunna beräkna installationstider för olika komponenter inom en komponentgrupp utan att behöva kunna kategorisera arbetstimmarna för varje enskild komponent. Konceptet bygger på att mäta ”referenstider” för olika komponenter inom en komponentgrupp och sedan antas att förhållanden för att installera komponenterna är alltid samma. Med denna metod räcker det med att kunna fastställa arbetstimmarna för hela komponentgruppen. Även om avhandlingen främst fokuserar på nödvändig datamätning, har exempelvis Lean-teorier använts för att analysera resultat.
Installationstiderna som undersökts i avhandlingen är väsentliga för produktionsplaneringen och beräkningen av produktionsbelastningen. De används även vid uppgörandet av investeringskalkyler inom produktionen. Av speciellt intresse är skillnaden på installationstiderna mellan block- och storblockutrustning, som varierar beroende på komponentgruppen. Installationstiderna fungerar som basis för de rekommenderade framtida nyckeltalen.
Utgångsläge-analysen tillsammans med processmätningarna tydliggör produktionens utmaningar, t.ex. otillräckliga förutsättningar, lågt kapacitetsutnyttjande och källor för variation. De otillräckliga förutsättningarna innebär t. ex. förseningen av design och saknande material. Variation föranledas från obalanserad planering av schema och manual natur av arbetet. I avhandlingen analyseras och jämförs byggnadsmetoden med ritningarna och själva produktionsfasen. Avhandlingen innehåller m.m. ett förslag för bättre byggnadsmetod med tillhörande arbetsordning för komponentgrupper inom samma fas.
På basis av utgångsläget och mätningarna rekommenderas det tre nyckeltal: andelen utförda installationsbilder och två olika nyckeltal för förseningar. Inom produktionen är det viktigt att vara medveten om förseningar i budgeten (beräknad i arbetstimmar) och vilken effekt den uppskjutna arbetsmängden har på den allmänna arbetsbelastningen. Dessutom rekommenderas det att fortsätta mäta installeringstiderna tills urvalet är flera än 30 stycken per komponentgrupp. På det sättet är det möjligt att komma närmare det riktiga medeltalet för installationstiderna och förekomsten av variation kan identifieras noggrannare.
Meyer Turkus målsättning är att fördubbla produktionstakten inom fem år. Med information från denna avhandling är det delvis möjligt att analysera varken de existerande utvecklingsprojekten är tillräckliga för att nå den önskade produktionstakten. Samma undersökning behöver utföras för områdesutrustning för att kunna forma en helhetsbild över hela utrustningsprocessen. Ur vetenskapligt perspektiv har denna avhandling tillagd kunskap till de existerande mätningsmetoderna. Innehållet skulle kunna utnyttjas för liknande undersökningar i maskinverkstäder eller liknande platser, som innehåller mycket manual arbete och variation.
The methods for conducting the study are practical by nature but theory is used to explain results. Data has been collected through interviews with stakeholders and measurements have been performed to support the validity of the first mentioned.
The obtained installation times for section and block outfitting are by far the most valuable contribution since they have enabled predicting workloads much more accurately and thereby assisting production planning. All the future yard outfitting schedules are based on the installation times provided in this thesis. In addition, these have been utilized as the basis for calculating future investments. Otherwise, more insight is provided on reporting to information systems, detail design and variation within production.
Meyer Turku aims to double its production tact within the next five years. This study partly enables evaluating the sufficiency of existing development projects i.e. gap plans. The area phase should be similarly studied though to reach holistic understanding. For the body of existing knowledge on topic, a new measurement technique, utilization of reference times, adds to practical examples for easing work analysis in highly manual circumstances with lots of variation e.g. metal workshops, in turn saving money.
Syftet med denna avhandling är att stöda produktionsplanering inom block- och storblockutrustning på Meyer Turkus skeppsvarv och kunna bidra till en mera balanserad arbetsbelastning inom produktion. Avhandlingen omfattar inte områdesutrustningen. Avhandlingen kan vara av intresse för dem som vill läsa mera om utmaningar inom utrustningsproduktion och hur man kan kombinera arbetsstudier med teorier om nyckeltal, identifiering av slöseri (Mura, Muri & Muda), variation och flöde i enlighet med Lean-metoden.
Avhandlingen omfattar fyra forskningsuppgifter: undersökning av utgångsläget genom intervjuer och processmätningar, mätningar av installationstider, undersökning av olika indikatorer samt rekommendation för framtida användning av nyckeltal. Avhandlingen bygger på skribentens tidigare undersökningar om block utrustning utförda sommaren 2017 och 2018.
Mätningsmetoderna baserar sig på sådana metoder som använts inom tidigare arbetsstudier, men denna avhandling innehåller ett nytt koncept för att underlätta insamlingen av rådata. Konceptet skapades för att kunna beräkna installationstider för olika komponenter inom en komponentgrupp utan att behöva kunna kategorisera arbetstimmarna för varje enskild komponent. Konceptet bygger på att mäta ”referenstider” för olika komponenter inom en komponentgrupp och sedan antas att förhållanden för att installera komponenterna är alltid samma. Med denna metod räcker det med att kunna fastställa arbetstimmarna för hela komponentgruppen. Även om avhandlingen främst fokuserar på nödvändig datamätning, har exempelvis Lean-teorier använts för att analysera resultat.
Installationstiderna som undersökts i avhandlingen är väsentliga för produktionsplaneringen och beräkningen av produktionsbelastningen. De används även vid uppgörandet av investeringskalkyler inom produktionen. Av speciellt intresse är skillnaden på installationstiderna mellan block- och storblockutrustning, som varierar beroende på komponentgruppen. Installationstiderna fungerar som basis för de rekommenderade framtida nyckeltalen.
Utgångsläge-analysen tillsammans med processmätningarna tydliggör produktionens utmaningar, t.ex. otillräckliga förutsättningar, lågt kapacitetsutnyttjande och källor för variation. De otillräckliga förutsättningarna innebär t. ex. förseningen av design och saknande material. Variation föranledas från obalanserad planering av schema och manual natur av arbetet. I avhandlingen analyseras och jämförs byggnadsmetoden med ritningarna och själva produktionsfasen. Avhandlingen innehåller m.m. ett förslag för bättre byggnadsmetod med tillhörande arbetsordning för komponentgrupper inom samma fas.
På basis av utgångsläget och mätningarna rekommenderas det tre nyckeltal: andelen utförda installationsbilder och två olika nyckeltal för förseningar. Inom produktionen är det viktigt att vara medveten om förseningar i budgeten (beräknad i arbetstimmar) och vilken effekt den uppskjutna arbetsmängden har på den allmänna arbetsbelastningen. Dessutom rekommenderas det att fortsätta mäta installeringstiderna tills urvalet är flera än 30 stycken per komponentgrupp. På det sättet är det möjligt att komma närmare det riktiga medeltalet för installationstiderna och förekomsten av variation kan identifieras noggrannare.
Meyer Turkus målsättning är att fördubbla produktionstakten inom fem år. Med information från denna avhandling är det delvis möjligt att analysera varken de existerande utvecklingsprojekten är tillräckliga för att nå den önskade produktionstakten. Samma undersökning behöver utföras för områdesutrustning för att kunna forma en helhetsbild över hela utrustningsprocessen. Ur vetenskapligt perspektiv har denna avhandling tillagd kunskap till de existerande mätningsmetoderna. Innehållet skulle kunna utnyttjas för liknande undersökningar i maskinverkstäder eller liknande platser, som innehåller mycket manual arbete och variation.